Once we have the plans back from the Architects' Association in Almeria, and have permissions from your local council, excavation can begin. Access into the site will have been decided at planning time, and if any fences or walls need removing, they will be replaced at the end of the build. If you have enough land, a good way to save money is to spread the earth on site. We can landscape this for you to provide features to enhance the poolscape. If you don't have enough space the spoil will be taken away in lorries.
The pool is precisely dug to allow the pool size plus the thickness of the concrete, which will be between 200-300mm (8-12"). At this time we also dig the trenches taking the pipes from the pool to the pump house, and to take the water and electricity supplies from the house to the pump house. The last excavation job is to dig the pump house base. |
|